ELKHORN ROAD / NORTH MONTEREY COUNTY — October 29, 2026. A regional drinking-water project has a specific proposed construction site along Elkhorn Road near Hudson Landing Road. In a planning item considered on August 12, 2026, Monterey County reviewed the Pajaro Sunny Mesa Springfield Area Regional Consolidation Project, which would combine several public and private sources into one larger water system.
What is planned on Elkhorn Road?
At an existing Sunny Mesa well property, identified as assessor’s parcel 117-121-003-000, the application calls for a transmission booster pump station to move water between the Pajaro and Sunny Mesa systems and then toward the Bluff/Jensen Road and Springfield service areas. Staff describe a proposed combined pumping capacity of 700 gallons per minute at this component and retention of existing Sunny Mesa wells as standby sources.
How big is the regional project?
The overall plan includes roughly 235,000 linear feet of pipeline, storage tanks, upgraded wells and treatment infrastructure. It is designed to serve approximately 967 connections when fully operating. The county identifies risks from contamination, flooding and the reliability of smaller systems as reasons for consolidation.
Which protections would apply?
Parts of the application require coastal permits because the infrastructure would be near sensitive habitat, archaeological resources and steep slopes; it also proposes removal of two coast live oak trees at the Elkhorn Road booster-station area. County staff recommended approval with 15 conditions and consideration of a previously adopted mitigated negative declaration.
Has the water infrastructure already been constructed?
The August 12 planning item does not verify construction completion, household connections or current service quality. It documents project scope and a review process. Residents should obtain the executed decision, district schedule, water-quality reports and notices for their particular account before assuming that their property is connected.
Primary source: Monterey County Planning Commission PC 26-076 / PLN250195, August 12, 2026. This article focuses on the documented Elkhorn Road facility within the larger North County project.
Support Elkhorn News
Choose how to support Elkhorn News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Elkhorn News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Elkhorn News
- Elkhorn Slough Reserve: How a Historic Woodland Plan Addressed 1,225 Eucalyptus Trees and 220 More →
- Elkhorn Road: 966-Square-Foot ADU Conversion Proposed for Existing Guesthouse and Workshop →
- Free Elkhorn Slough Reserve Guided Walks This Weekend: What Visitors Must Know →
- Brothers Ranch Restoration: California Issues State Permit for Elkhorn Slough Hydrology Project →
СООБЩЕСТВО
Комментарии
Присоединяйтесь к обсуждению California58. Чтобы комментировать, необходимо войти в аккаунт.
Создайте бесплатный аккаунт California58 или войдите через доступную социальную сеть.